To download a pdf of this briefing:
http://home.comcast.net/~clay_harper/CaseyArbrowayBrief.1.pdf
EXECUTIVE SUMMARY
- The Casey Overpass in Jamaica Plain is beyond
repair and must be demolished for
public safety
- Offers an historic opportunity to reconnect broken portions of the Emerald
Necklace and improve livability through contemporary urban and traffic planning
- For nearly three years citizens, neighbors and other advocates have participated in an open
process with MassDOT professionals to
design a replacement. Twenty-two Advisory Group meetings were held and seven larger Public
Hearings took place to update the
community.
- MassDOT selected an At-Grade Solution, a
simplified network of surface roads
in March 2012 and the majority of the community hailed the
choice
- Peer-reviewed traffic projections indicate no
significant drop in level of service for
any affected routes, and some improvement for many. Air quality
analysis shows no change.
- Significant opportunity to improve multi-modal
access for cars, bicycles, and
pedestrians to the area parks and businesses
- Enhanced access to MBTA services: a new head house and upper bus way.
- New and enhanced plazas north and south of Casey
Arborway could accommodate festivals
and farmer’s markets
- Improved civic space at the West Roxbury District Court
- A tree-lined boulevard and coordinated lights replace a crumbling bridge
- Construction and maintenance cost savings are estimated to be at least $20
million if the bridge is not replaced
- Planning and design is nearly final
- Opportunities for Elected Official leadership in constituent services, construction
mitigation, adjacent-area improvements, economic development
- Demolition scheduled to begin in spring 2014,
construction to last until fall 2016
STATUS AND HISTORY
The Monsignor William J. Casey Overpass was built in
the early1950s on a portion of the Arborway parkway of the Emerald Necklace in
the Forest Hills section of Jamaica Plain. Due to flaws in its original design
and the deterioration of its structural integrity over the last 60 years, it is
now beyond repair and must be demolished. For safety, vehicle traffic has been
reduced to one lane in each direction for more than two years (from the
original six lanes) while a replacement solution is designed. The community
outreach and design process undertaken by MassDOT and its partners the City of
Boston, DCR and MBTA has been ongoing for nearly three years to date. Engaging
hundreds of professionals and local citizens in dozens of public meetings, the
plans have been improved and have incorporated community input to the extent
possible at every juncture. Demolition of the Overpass is scheduled to begin in
the spring of 2014. The project will be completed in Fall 2016.
The Jamaica Plain, Forest Hills,
Roslindale and West Roxbury neighborhoods in the shadow of the overpass are
characterized by an abundance of greenspace and recreational opportunity, by an
inviting mix of residential properties and vibrant commercial enterprises, by
active community engagement in schools and other civic life and by access to
convenient public transportation. Boston’s world-renowned Emerald Necklace
parkways, Southwest Corridor Park, Franklin Park, and the Arnold Arboretum are
immediately adjacent to the project, as is the Forest Hills MBTA station.
Forest Hills has been an important
transit hub for nearly 200 years. When the Overpass was built, its huge ramps,
supports and abutments spanned three different rail lines. A heavy rail
embankment crossed the bridle paths and carriageways of the Arborway atop a
handsome, five-arched bridge from the 1890s until it was torn down in 1986. The
street-level Arborway trolley line made its way under this viaduct from South
Street to the Arborway Yard from the 19th century until the
mid-1980s. The elevated Orange
line ran above Washington Street on steel beams and huge concrete posts from
the 1910s until 1986, culminating in a large station that served the El above,
trolleys, buses and cabs below.
The Casey Overpass leapt over all
this, as well as Washington Street, Hyde Park Avenue and South Street – major
north-south thoroughfares for the surrounding neighborhoods.
The span of the Overpass, with its
huge piers below, was built on the land that once carried eastbound Arborway
traffic from Boston. It bypassed rail and trolley congestion below, and was
built for vehicles going to and from Mattapan, Dorchester, Quincy and Milton.
All local traffic seeking the businesses and residences of southern Jamaica
Plain, Forest Hills, Roslindale, the Walk Hill and Bourne neighborhoods or the
West Roxbury District Court was required to exit the Arborway and wind through
and around these piers and ramps via convoluted and inefficient paths that
disrupted the flow of traffic on the ground further, requiring transit of as
many as four traffic lights for what should be simple and routine pathways.
More than twenty-five years ago the
Orange line and the heavy rail lines were brought together and sunk below grade
in the Southwest Corridor Trench. A new MBTA station was built and the old
station and granite viaduct of the New Haven line were demolished. The Arborway
trolley ceased operations at the same time. This mid-1980s transformation of
Forest Hills eliminated the surface congestion of the three rails lines that
the Overpass was built to span. The Overpass ramps and supports continue to
impede street-level traffic, as they have since the 1950s.
CONTEXT
National and international urban
planning initiatives have for decades called for a more equitable access for
all transit modes, and Boston’s planning has been no exception. As Mayor Menino
has stated, “The car is no longer king in Boston.” All across the country
cities, including Boston, have been saying “No” to building or replacing urban
overpasses that divide neighborhoods and increase the tax-funded maintenance
burden far into the future.
Boston’s own Complete Streets approach puts pedestrians, bicyclists and transit
users on equal footing with motor-vehicle drivers. The initiative aims to
improve the quality of life for Bostonians by creating streets that are both
attractive public spaces and sustainable transportation networks. It embraces
innovation to address climate change and promote healthy living. The objective
is to ensure that Boston's streets are:
- Multimodal:
Incorporates pedestrians, people with disabilities, bicyclists, transit
users, and motor vehicle drivers. Roadway design includes level of service
benchmarks for all modes to ensure that streets are shared by all users
and not dominated by cars.
- Green:
Incorporates street trees, rain gardens, green margins, and paving
materials with permeable surfaces so that plants and soils collect
rainwater to reduce flooding and pollution. Green design elements promote
an environmentally sensitive, sustainable use of the public right-of-way.
- Smart:
Incorporates intelligent signals, smart meters, electric vehicle sharing,
car and bicycle sharing, way-finding and social networks for greater
system efficiencies and user convenience.
MassDOT’s GreenDOT initiative, begun in 2010, has goals aligned with
Boston’s Complete Streets and
with contemporary planning tenets. It has a mode shift goal of tripling the
share of travel in Massachusetts by bicycling, transit and walking by 2030.
OPPORTUNITY
The Casey Arborway Project has
enlisted hundreds of local citizens and engaged thousands more over nearly
three years in an open, collaborative process that has considered all of these
aspects in an effort to find the best possible solution for this complex 21st
Century transportation and urban planning opportunity. The professionals,
advocacy groups and ordinary citizens all agree that the Casey Arborway
replacement provides
- A once
in a generation opportunity to improve the efficiency of travel and access
to the area for all modes (car, pedestrian, bike, public transportation)
- A once
in a lifetime opportunity to enhance livability through improved civic
spaces, enlarged greenspaces, and a restoration of the Emerald Necklace in
Forest Hills – a recreational connection that has been broken for a
century.
- The
chosen At-Grade solution has the active support of parks, livability, and
cycling advocacy groups who have offered their expertise throughout the
planning process: Emerald Necklace Conservancy, Walk Boston, Boston
Cyclists Union, LivableStreets, Arborway Coalition.
- These
groups are engaged with tens of thousands of Bostonians who care deeply
about all these issues – parks, open space, pedestrian and cycling access,
public transportation - and they applaud the Casey planning work that has
been done so far. Their active input and that of local citizens and
neighbors of the project has been invaluable in improving the outcome and
in encouraging MassDOT to embrace this historic opportunity.
THE PROCESS TO DATE
The
Casey Overpass was a poor design from the start, with hammerhead piers that
have decayed severely and drainage schemes that have further contributed to
deterioration. Critical repairs were conducted in 1980 and 1991. MassDOT
maintenance inspections determined in early 2010 that the Overpass load rating
must be reduced to 14 tons. It was found that reducing traffic to one lane in
each direction and moving traffic away from the outer lanes and towards the
center for safer operation was the best option for achieving necessary load
reduction. In December 2011, it was determined that the Overpass was in
“critical to fair” condition, and nearing the end of its serviceable life. The
planning process for its replacement was begun.
A
Working Advisory Group (WAG) comprised of citizens, neighbors and advocacy
groups representing neighborhoods, parks, cycling, and livability was formed to
augment and advise the professional planning processes. This open and public
committee met more than twelve times, and five larger Public Hearings were held
in the community before MassDOT announced a final decision on a replacement
approach. Scores of different alternatives were evaluated, including those
suggested by members of the WAG and the general public.
Baseline traffic data was acquired
during this process for the Overpass itself and 17 intersections in the area in
early June 2010, while the Overpass still had two open lanes in each
direction. The average weekday
daily volume for the Overpass was found to be 24,000 cars (both directions, all
day). New Washington Street below was found to have an additional east-west
volume of 12,000 cars per day.
It was known that an overpass could
serve traffic loads in the area, but any other alternative needed thorough
study. The traffic data was projected out to the year 2035 using accepted
projection methodology. Travel routes, transit times and circulation patterns
throughout this complex area were measured and evaluated in a point-to-point
matrix, projected into the future and then applied to both an improved at-grade
street arrangement and a two-lane replacement overpass. The data collected and
methodology used was peer-reviewed by outside transportation experts.
Both plans showed improvement over
the current overpass and street configuration. But through this data testing
process it was determined that drivers would experience no significant
degradation or favorability in service with either plan. The levels of service
for some routes showed marginal slowing (30-45 seconds), while the majority of
routes were either time and distance neutral, or marginally improved.
Because of the comparable travel
times and distances, Air Quality analysis showed no predicted degradation in
air quality.
The cost projections provided by
consultants, however, showed a very significant difference between the two
alternatives under consideration: an estimated $74 million cost for a new
overpass (plus substantial future maintenance obligations for the 75-year life
of the structure), or $54 million cost for an at-grade configuration.
MassDOT announced its decision to
select and develop a so-called “At-Grade Solution” to be known as the Casey
Arborway in March 2012. The existing ramps, abutments and supports of the
Overpass will be replaced by a simplified series of intersections on the ground
using coordinated lights, a plan that offers significant opportunities to
return the area to human scale and enhance livability for residents and
visitors alike.
MassDOT immediately formed a new
Design Advisory Group (DAG) to consult on the planning, to voice community
concerns and to refine project priorities. The DAG met ten times over 18
months, and focused on a variety of important topics at each meeting.
Additional public hearings were held to update the larger community at the 25%
and 75% design stages, to hear concerns and to report on progress.
PLAN HIGHLIGHTS
- The
creation of a tree-lined boulevard where the unsightly shadow of a
crumbling overpass now stands.
- Simplified
turns and north-south routes throughout Forest Hills with coordinated
lights directing the flow of traffic.
- A new
MBTA head house on the north side of the Casey Arborway, which will
provide direct access to the Orange line platform without crossing what is
now New Washington Street.
- A new
northern Plaza at the end of Southwest Corridor Park, which provides
significant civic space suitable for gatherings, festivals, farmer’s
markets and community events.
- An
enhanced entrance plaza adjacent to the MBTA station on the south side of
Casey Arborway will provide improved waiting and gathering space as well
as room for retail kiosks.
- The
#39 bus terminus will be relocated to an expanded upper bus bay along
Washington Street.
- Significantly
improved civic spaces in the District Court House area.
- Dedicated
bicycle and pedestrian paths and crossings throughout the area
- A
strengthened and more accessible connection from Franklin Park to the
Casey Arborway, Arnold Arboretum and the rest of the Emerald Necklace
parks, as well as to Southwest Corridor Park.
- Enhanced
way-finding for visitors and residents navigating the area on foot, by
bicycle, by public transportation and by private vehicle.
- Increased
access to the world-class recreational opportunities and the vibrant
businesses of Forest Hills and Jamaica Plain.
The Casey project planning has also
included significant regulatory review.
Environmental Justice and Air Quality reviews were conducted and
Massachusetts Environmental Policy Act certification was achieved.
MassDOT and the Massachusetts
Historical Commission are currently considering a finding of ‘adverse effect’
in the preferred plan at Shea Circle. Shea Circle has one of the state’s
highest rates of single-vehicle car accidents, and MassDOT has proposed to
create a signalized intersection known as “Shea Square”. This proposal provides
significant traffic calming as well as a configuration that is more serviceable
for pedestrians and cyclists while expanded the acreage of useable greenspace.
The DAG and the majority of the local community has valued public safety and
enhanced access to Franklin Park over the existing large traffic rotary, which
has no traffic lights and little traffic calming effect. But Shea Circle, a
feature not part of Olmsted’s original design and not built until the 1930s, is
in fact part of the Morton Street Historic District, on the National Registry
of Historic Places and subject to MHC review. The outcome of this consideration
has yet to be determined as of this writing.
NEXT STEPS
MassDOT’s final design is nearly
complete. Construction phasing and detouring plans have been outlined.
Landscaping schemes are being refined. Major features – the plazas, bus ways,
bicycle and pedestrian paths and major intersections – have been designed.
Provisional construction blue prints have been prepared. MassDOT is making
final refinements through an internal review process, will host a final DAG
meeting and then intends to advertise the project and solicit bids in October
or November 2013. Construction is expected to begin in the spring of 2014 and
be completed in the fall of 2016. Any significant changes to the plan at this
point could substanially increase the cost of the project and could result in
increased safety risks.
OPPORTUNITIES FOR ELECTED OFFICIAL LEADERSHIP
Demolition and construction/mitigation management
During
any construction project as large as this one - immediately adjacent to residential
neighborhoods, retail and commercial enterprises and a thriving transit hub -
there will likely be issues requiring strong leadership:
- Education,
information and preparation concerning Construction Phasing
- Sound
and dust mitigation, hours of construction, planned detouring and closures
- Policing:
Traffic management, parking and speed enforcement, signage
- MBTA
and school bus service levels and contingencies
- Constituent
services/Hot-lines
- Disruption
and traffic delays would occur no matter what the replacement design
Planning for adjacent features
Consideration should be given to
improving adjacent city-owned properties to leverage final outcome:
- “Don’t
Block the Box” signage and striping on South Street at Arborway Road
- Sidewalk
improvement along Forest Hills Avenue adjacent to the Arborway Yard
- DCR
should construct the long-planned pathway through the Arborway Hillside,
from South Street to the Arboretum as outlined in the 2008 Gateway to the
Arborway plan.
Housing and economic development
The future Casey Arborway and
Forest Hills’ proximity to mass transit is making the surrounding area a magnet
for new housing and commercial development. While this will provide much-needed new housing and job
opportunities, it also presents challenges for elected officials.
- Private
development will need to be coordinated with the state’s construction
schedule for the Casey Arborway and residents will look to the City to
provide both enforcement and a vision for the neighborhood as it evolves.
- In
2008, after a lengthy community process, the BRA released the Forest Hills
Improvement Initiative, which provided development guidelines for MBTA and
private property. Two of
those parcels have already been developed as commercial/office space and a
third is slated for new housing and retail. Additional proposals are currently under review
to convert former industrial sites along nearby Washington Street to
housing, retail, and commercial space.
- Parcel
U (along Hyde Park Avenue) is slated for retail and housing. Developers of
the former Hughes Oil site are seeking zoning approvals with an emphasis
on desirability of multi-modal transit access dependent on improved
traffic patterns, diversity, mixed-use, community spaces, as well as
improved greenspace and recreational access.
- Neighborhood
residents have requested additional planning to guide new development
adjacent to the north side of the Casey Arborway, which was not included
in the FHII.
- The
existing MBTA Arborway Yard facility has been envisioned as home to a new
MBTA bus yard. The state has agreed to provide 8 acres of land to the City
of Boston for housing, commercial use, and open space. Elected officials
will need to be a strong advocates for state funding to bring the project
to fruition, as well as work with the neighborhood to plan for its
redevelopment.
The Casey Arborway Project offers
an unprecedented opportunity to bring positive change to several of Boston’s
premier neighborhoods. By reconnecting long-broken links within the Emerald
Necklace parks and by providing enhanced access for pedestrians and cyclists
that fulfill the promise of Southwest Corridor Park, the Casey Arborway and
Forest Hills will become a citywide recreational magnet, an attractive locale
for retail and housing development, as well as a much-improved version of the
transportation hub it has been for more than a century.
SOURCES AND RESOURCES
For a complete record of all public meetings, including
meeting minutes, attendees, public comment and professional presentations:
Many relevant documents, reports, data and long-range
planning resources related to the project are collected here:
Participants and partners in the WAG and DAG process are
here:
For a pictorial history of the Arborway and Overpass at
Forest Hills:
A complete history of Forest Hills is available here:
Boston’s Complete Streets initiative:
MassDOT’s GreenDOT:
The Forest Hills Improvement Initiative is guiding
development in the area
The Congress for the New Urbanism’s Highways to
Boulevards project documents revitalized
urban centers where overpasses and highways have come down:
Prepared by
Clayton Harper/ArborwayMatters
44 Hampstead Rd
Jamaica Plain, MA
clay_harper@comcast.net
617.388.4568
#ArborwayMatters